CENTRAL GROUND WATER AUTHORITY (CGWA), GROUND WATER NOC FOR INDUSTRIES

CENTRAL GROUND WATER AUTHORITY (CGWA), GROUND WATER NOC FOR INDUSTRIES

Fill the form & connect with us

You can learn more about our services and procedures and ask us your questions via online contact form! Our representative will gladly reply to you shortly!

Overview

All industries/ mining/ infrastructure dewatering projects, whether existing/ new/ under expansion and drawing/ proposing to draw ground water through energized means shall need to obtain NOC for ground water withdrawal from the Central Ground Water Authority.

Documents required to file Ground Water NOC :-

  • Consent to Establish from State Pollution Control Board
  • Affidavit on non-judicial stamp paper of Rs. 10/- by the applicant, confirming non/ inadequate availability of public water supply ( in case of water requirement is less than 10 KLD)
  • Certificate of non/partial availability of water from local government water supply agency in respect of all categories of assessment units. (Required in case of water requirement
  • Ground water quality report of existing ground water abstraction structure from NABL accredited/govt. approved lab
  • MSME Certificate in case of MSME (in case of water requirement is more than 10 KLD in OE areas, for new projects only)
  • Approval from Wetland Authority (in case of Project area falling within 500 meter of Wetland zone)
  • Bharatkosh receipt for depositing Application Fee
  • Source Water Availability/Non-availability Certificate
  • Aplication with Signature and Seal